Recommendation
A. Authorize the City Manager to execute Amendment No. 3 to Agreement No. 2023-033 with UNICO Engineering, Inc. for Professional Construction Management Services for Project Connect, increasing the agreement amount by $232,241.35 for a total not-to-exceed amount of $6,405,487.71 and a termination date of December 31, 2027;
B. Authorize the City Manager to execute Amendment No. 4 to Agreement No. 2019-023 with Dewberry Engineers, Inc. for Professional Design Services for San Jose Creek Multipurpose Path, increasing the agreement amount by $897,495 for a total not-to-exceed amount of $6,229,905 with a termination date of June 30, 2028; and
C. Authorize a budget appropriation in the amount of $17,958,696.61 as identified in Table 5 of the Fiscal Impacts section of the staff report.
Staff
Luz “Nina” Buelna, Public Works Director
Sarah Fox, Public Works Business and Administration Manager