Recommendation

A.                     Receive a presentation on the preliminary five-year (2023/2024 - 2027/2028) Capital Improvement Program project delivery and preliminary cost estimates;

 

B.                     Reject all bids for Hollister Old Town Interim Striping Project;

 

C.                     Direct staff to return to City Council on December 5, 2023 to award Project Connect, and include the proposed funding strategy, and related budget adjustments and appropriations;

 

D.                     Direct staff to negotiate a construction change order to Project Connect to construct the Hollister Old Town Interim Striping Project and return to City Council on December 19, 2023 to approve a change order for the Hollister Old Town Interim Striping Project;

 

E.                     Authorize the City Manager or his designee to request an amendment to the Measure A Investment Plan by the Santa Barbara County Association of Governments to transfer the $8.4 million in Measure A regional funds from the named Goleta US 101 Overcrossing project to the Goleta Transportation Circulation Improvements Project; and

 

F.                     Direct staff to come back in April 2024 to further review the CIP project delivery and options for funding these projects.

 

 

Staff

Charles W. Ebeling, Public Works Director

Autumn Glaeser, Capital Improvement Program Manager