Title: Award of Construction and Construction Management, Inspection and Testing (CMIT) Contract for the Hollister/Kellogg Park Project and San Jose Creek Bike Path Middle Extent Segment 1
Attachments: 1. Award of Construction and Construction Management, Inspection and Testing (CMIT) Contract for the Hollister/Kellogg Park Project and San Jose Creek Bike Path Middle Extent Segment 1 - Staff Report
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Recommendation

A.                     Authorize the City Manager to execute a construction contract with C.S. Legacy Construction, Inc.                     for the Hollister/Kellogg Park Project in an amount not to exceed $3,592,171, subject to the requirements of the contract documents (Attachment 1); and

 

B.                     Authorize the City Manager to approve contingency contract change orders for the Hollister/Kellogg Park Project, if necessary, in an amount not to exceed $538,825; and

 

C.                     Authorize the City Manager to execute a consultant services agreement with Filippin Engineering, Inc., in an amount not to exceed $467,709 for Construction Management, Inspection and Testing (CMIT) Services for the Hollister/Kellogg Park Project (Attachment 2); and

 

D.                     Approve an additional appropriation of $826,293 from Fund 221 (Park DIF) to CIP Project 9035 - Hollister/Kellogg Park Project account 221-5-9035-706.

 

 

Staff

JoAnne Plummer, Parks and Recreation Manager

Teresa Lopes, Senior Project Engineer