File #: 18-410    Version: 1 Name:
Type: Consent Item Status: Agenda Ready
File created: 9/19/2018 In control: City Council
On agenda: 10/16/2018 Final action:
Title: Approve Revised Project Plans and Specifications and Award of Construction Contracts for the Crosswalk at South Kellogg Avenue Project
Attachments: 1. Approve Revised Project Plans and Specifications and Award of Construction Contracts for the Crosswalk at South Kellogg Avenue Project - Staff Report
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Recommendation

A.                     Approve revised Plans and Specifications for the Crosswalk at South Kellogg Avenue Project; and

 

B.                     Authorize the City Manager to execute a construction contract with Toro Enterprises, Inc. for the Crosswalk at South Kellogg Avenue Project in an amount not to exceed $129,965, subject to the requirements of the contract documents (Attachment 1); and

 

C.                     Authorize the City Manager to approve contingency contract change orders for the Crosswalk at South Kellogg Avenue Project, if necessary, in an amount not to exceed $26,000; and

 

D.                     Authorize the City Manager to execute a consultant services agreement with Filippin Engineering, Inc., in an amount not to exceed $28,875 for Construction Management, Inspection, and Testing Services for the Crosswalk at South Kellogg Avenue Project (Attachment 2); and

 

E.                     Authorize an additional appropriation of $25,076 from Fund 402 (CDBG Fund) to CIP Project No. 9098 - Crosswalk at South Kellogg Avenue Project account 402-5-9098-705, and increase CDBG grant revenues account 402-4-8500-222 by $25,076; and

 

F.                     Authorize an additional appropriation of $80,405 from Fund 205 (Measure A) to CIP Project No. 9098 - Crosswalk at South Kellogg Avenue Project account 205-5-9098-705.

 

 

Staff

James Winslow, Senior Project Engineer