File #: 19-004    Version: 1 Name:
Type: Consent Item Status: Agenda Ready
File created: 12/13/2018 In control: City Council
On agenda: 1/15/2019 Final action:
Title: Award of Construction Contract and Construction Management, Inspection, and Materials Testing Services Agreement for the Fairview Avenue Sidewalk Infill at Stow Canyon Road Project (CIP 9060)
Attachments: 1. Award of Construction Contract and Construction Management, Inspection, and Materials Testing Services Agreement - Staff Report

Recommendation

A.                     Authorize the City Manager to execute a construction contract with Lash Construction, Inc., for the Fairview Avenue Sidewalk Infill at Stow Canyon Road Project in an amount not to exceed $395,989, subject to the requirements of the contract documents (Attachment 1); and

 

B.                     Authorize the City Manager to approve contingency contract change orders for the Fairview Avenue Sidewalk Infill at Stow Canyon Road Project, if necessary, in an amount not to exceed $79,000; and

 

C.                     Authorize the City Manager to execute a professional design services agreement with Filippin Engineering, Inc., in an amount not to exceed $86,800 for Construction Management, Inspection, and Materials Testing Services for the Fairview Avenue Sidewalk Infill at Stow Canyon Road Project, with a termination date of June 30, 2020 (Attachment 2); and

 

D.                     Authorize an additional appropriation of $507,285 from Fund 220 (GTIP) to CIP Project No. 9060 - Fairview Avenue Sidewalk Infill at Stow Canyon Road Project account 220-5-9060-705.

 

 

Staff

Charles Ebeling, Public Works Director

Melissa Angeles, Senior Engineering Technician