Recommendation
A. Authorize the City Manager to execute Amendment No. 3 to Professional Design Services Agreement No. 2016-114 with TJKM for the Hollister Complete Streets Corridor Plan Project (9001) to extend the agreement to June 30, 2021 (Attachment No. 1);
B. Authorize the City Manager to execute Amendment No. 3 to Professional Design Services Agreement No. 2016-143 with MNS Engineers, Inc., for the Hollister Class I Bike Path Project (9039), increasing the maximum contract amount by $20,600 for a total amount not-to-exceed $548,136, and extending the agreement to December 31, 2020 (Attachment No. 2); and
C. Authorize the City Manager to execute Amendment No. 4 to Professional Design Services Agreement No. 2016-040 with Drake Haglan and Associates, for the Hollister Class I Bike Path Project (9039) extending the agreement to June 30, 2020 (Attachment No. 3).
Staff
Charles W. Ebeling, Public Works Director
Teresa Lopes, Senior Project Engineer