Recommendation
A. Receive an update on the Ekwill Street and Fowler Road Extensions Project and the Hollister Avenue Bridge Project;
B. Authorize the City Manager to execute Amendment No. 8 to Professional Design Services Agreement No. 2012-090 with Dewberry Engineering, increasing the contract authority by $548,798, for a new total contract amount of $4,832,070, for the Ekwill Street and Fowler Road Extensions Project, and extend the term to June 30, 2024; and
C. Authorize the City Manager to execute Amendment No. 6 to Professional Design Services Agreement No. 2013-028 with Dewberry Engineering, increasing the contract authority by $397,624, for a new total contract amount of $2,571,535, for the Hollister Avenue Bridge Project, and extend the term to June 30, 2024.
Staff
Charles W. Ebeling, Public Works Director
Gerald Comati, Project Manager
Estimated Time
60 minutes